Changing the Status of RCM2 Failure Modes and Analyses

You can keep track of the strategy development process by monitoring and changing the status of analyses and failure modes. For example, the site’s Strategy Development view and tab, RCM2 tab displays the statuses of the analyses in the Analysis status column:
To view the statuses of failure modes, open the analysis, select the RCM2 Explorer view and then the Information worksheet node. The Action plan status column displays each failure mode’s status. For example:
The following table shows typical activities and the appropriate status of the analysis and its failure modes. The analysis statuses are also used for templates.
When working with failure modes, keep the following in mind:
When working with the status of analyses, keep the following in mind:
Tip: You can review the history of analysis status changes on the History view, Analysis Audit Info tab.
This topic explains how to change the status of failure modes and analyses.

To Change the Status of a Failure Mode

1.
Select the site’s Strategy Development view and tab, and select the RCM2 tab.
2.
Open the analysis containing the failure mode. Select the Facilitation view and the Info Worksheet tab.
3.
To complete a failure mode with a recommended action, right-click it, click Mark As, and then Facilitation Completed, Implementation Completed, or Implementation Not Required.
To reopen a completed failure mode, right-click it, click Mark As, and then Facilitation Incomplete.

To Change the Status of an Analysis or Template

You can change the status of analyses that have the status Analysis Completed or Closed.
1.
From the site’s Strategy Development view and tab, select the RCM2 tab.
Tip: You can also view the list of analyses from an asset’s Strategy Development view and tab, Analyses tab.
2.
Right-click the analysis, click Mark as, and then the status.
Open the analysis, click the Tools menu, Mark As, and then the status.