Changing the Status of RBI Failure Modes and Analyses

You can keep track of the strategy development process by monitoring the status of analyses and failure modes. For example, the site’s Strategy Development view and tab, RBI tab displays the statuses of the analyses in the Analysis Status column:
To view the statuses of failure modes, open the analysis, select the Facilitation view and then the Info Worksheet tab. The Action plan status column displays each failure mode’s status. For example:
The following table shows typical activities and the appropriate status of the analysis and its failure modes.
When working with action plans, keep the following in mind:
When working with the status of analyses, keep the following in mind:
Tip: You can review the history of analysis status changes on the History view, Analysis Audit Info tab.
This topic explains how to change the status of failure modes and analyses.

To Change the Status of a Failure Mode

1.
From the site’s Strategy Development view and tab, select the RBI tab.
2.
Open the analysis containing the failure mode. Select the Facilitation view and the Info Worksheet tab.
3.
To reopen a completed failure mode, right-click it, click Mark As, and then Facilitation Incomplete.

To Change the Status of an Analysis

1.
From the site’s Strategy Development view and tab, select the RBI tab.
Tip: You can also view the list of analyses from an asset’s Strategy Development view and tab, Analyses tab.
2.
Right-click the analysis, click Mark as, and then the status.
Open the analysis, click the Tools menu, Mark As, and then the status.