Changing the Planner on Work Order Tasks
If there are many work order tasks assigned to a planner, replacing the employee manually would be time consuming and prone to errors, therefore applying a mass update is a more efficient method. For more information about applying mass updates, see Applying Mass Updates.To Change the Planner on Work Order Tasks
1.
2. Select the Tasks tab.
4. Right-click the Planner column heading and select Replace. The Replace Column Data dialog appears. For example:
5. Enter the exact value that you want to replace all values in the column with or clickto select from a list of valid values, otherwise, click Blank to erase all information in the column.
6. Click Apply to perform the mass update. A dialog prompts you for confirmation. For example:
7. Click Yes to proceed.
8. When the update is complete, the status of the updates is displayed in the Status section. For example:
9. If rows could not be updated during a mass update, they can be viewed by clicking View Log or by APM administrators in the Mass Update Requests log. For more information, see Viewing Mass Update Requests.
11. Remove the filter applied in step 3. The changes are now reflected in the table.