Updating Actual Work Completion Status in Exported Schedules

Once work begins, you can update the work completion status for work order tasks on a schedule that you have exported to MS Project. The work progress is updated based on activity reported against the work order task in APM.
When you update the actual work completion status for tasks on a schedule, the following information is updated in the MS Project file:

To Update Microsoft Project Actuals

1.
2.
3.
From the Tools menu, select MS Project, and then select Update Actuals. APM updates your MS Project file based on activity reported against the work order task in APM.