Exporting Schedules to New Microsoft Project Files

This topic explains how to export one or more schedules to a new Microsoft Project file.
When you export a schedule to Microsoft Project, APM creates a Project file with the current contents of your APM schedule, including scheduled tasks, labor requirements, assignments, and availability. APM creates columns in Project’s standard views to display APM work order, asset, and scheduling data.
You can export your schedule to one or more new Project files or to an existing one. When you re-export a schedule, you can export the entire schedule or only changes you have made. You can also export a set of APM schedules to a new or existing Project file.

To Export one or More Schedules to a New Microsoft Project File

1.
Tip: To export a set of schedules, open the parent schedule for the set.
2.
3.
From the Tools menu, select MS Project and then Export. The MS Project Export dialog appears.
4.
Select Create a new project file.
5.
The source of the Microsoft Project file. Options are from Scratch or Based on a template. If Based on/Template is selected, enter the path to the template file. Template files must have the extension .mpt.
6.
7.
In the Project files to create section, select from the followng:
8.
In the Create a Project task for each section, select which summary tasks to create:
9.
10.
Click OK. APM creates the MS Project file, copies your schedule's information, and opens the new MS Project file.