Viewing Schedule Entry Relationships

If a work order task has relationships to other tasks, the relationships (dependencies) are copied to the schedule entry when the task is scheduled. This topic explains how to view task relationships from a schedule entry.

To View Schedule Entry Relationships

1.
2.
Select the Worksheet view, Entries tab. By default, this tab displays a list of all scheduled tasks by work order and task.
3.
Locate the Scheduling Dependencies column in the table. This column shows a summary of the relationships for this task.
4.
5.
Select the General tab, and then the Dependencies tab. The existing relationships are listed.
6.
7.
8.