The total number of items that are required. For example, the number of employees or contractors required for the trade or the number of tools.
The amount of time that each employee, contractor, tool, or service person is required. For example if you are entering a trade requirement, enter how long each employee will need to work on this task. The total time entered for the requirement will be calculated as:Number Of x Required For
Number of x Required for
• Start to start (SS): The requirement starts when the task is planned to start, offset by any entered lag time.
• Finish to finish (FF): The requirement ends when the task is planned to end. The system automatically calculates the required lag time.
This setting is used when calculating the estimated duration of the task, and when the task is scheduled.
You can specify the approval route to use for work order requirements created from this standard task requirement. To do this, select the option Use the approval route entered below, and then select the appropriate route.If you select the option The approval route will be identified when the work order is sent for approval, users will be able to choose from a list of appropriate route.