The total number of items that are required. For example, the number of employees or contractors required for the trade or the number of tools.
The amount of time that each employee, contractor, tool, or service person is required. For example if you are entering a trade requirement, enter how long each employee will need to work on this task. The total time entered for the requirement will be calculated as:Number Of x Required For
Number of x Required for
The name of the employee or contractor assigned to this trade requirement.You will only be able to assign someone to the requirement if the entry in the Number required box is “1”. You cannot assign multiple people to a single trade requirement. To assign multiple people, you must create multiple trade requirements (each with the Number required set to “1”).
• Start to start (SS): The requirement starts when the task is planned to start, offset by any entered lag time.
• Finish to finish (FF): The requirement ends when the task is planned to end. The system automatically calculates the required lag time.
This setting is used when calculating the estimated duration of the task, and when the task is scheduled.
Maintenance: Use for trade requirements that will be assigned to employees or on-site contractors (when the demand is on a work order task).Purchase: Use for trades, materials, tools, or services that need to be purchased.Warehouse Issue: Use for material that will be issued from a warehouse.Warehouse Transfer: Use for materials that will be transferred from one warehouse to another.Tool Issue: Use for tools that will be issued from a warehouse.Equipment Rental: Use for tools and equipment to be rented from an outside supplier.
• Regular purchase (used for most purchases)
• Equipment rental (used for tool resources only)
• Repair order (used for serialized units only)
• Service order (used for service resources only)
• On-site contractor (used for setting up the procurement process for on-site contractors)
•
• In planning: The RFQ resource has this status until the RFQ is sent to all suppliers.
• Waiting for bids: The RFQ resource has this status after it has been sent to all suppliers and before all of the supplier bids have been entered.
• All bids received: The RFQ resource has this status after all supplier bids have been entered.
• Analyzed: The RFQ resource has this status after a user has ranked the suppliers bids for the resource.
• Awarded: The RFQ resource has this status after it has been awarded to the winning supplier or suppliers.
• Cancelled: The RFQ resource has this status if a user has cancelled the RFQ.