Project File
The name of the MS Project file currently linked to the schedule. The name of the file to which the schedule was previously exported is defaulted. You can change it, for example, if the file has been renamed or moved.
If you are importing data from a MS Project file, enter file that will be imported. If you identify a Microsoft Project file that did not originate from the schedule, the file contents are bypassed. Only tasks that were created by an export function of this schedule are processed by the import.
See Also

Import Sub-projects
This option is only available if a master/sub-project structure was created when the schedules were exported. If you select this option, the current schedule's descendants are also imported from the MS Project files.
See Also

Yes, I have finished working with the Project file
You can select this box to clear the link between the exported APM schedule and the MS Project file — the restrictions on scheduling functions in APM are removed.